RESOLUTION NO. 19-9600
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF OPA-LOCKA, FLORIDA, AUTHORIZING THE CITY
MANAGER TO EXECUTE CHANGE ORDERS 1 AND 2 TO
THE AGREEMENT WITH DIAMANTI CONSTRUCTION AND
DEVELOPMENT, INC, FOR BAHMAN AVENUE PHASE II
SANITARY SEWER CONSTRUCTION IN AN AMOUNT NOT
TO EXCEED TWENTY-SIX THOUSAND FOUR HUNDRED
TWENTY-THREE DOLLARS AND EIGHTY-TWO CENTS
($26,423.82); PROVIDING FOR INCORPORATION OF
RECITALS; PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the City of Opa-locka ("City") entered into an agreement with
Diamanti Construction and Development, Inc for sanitary sewer construction on Bahman
Avenue; and
WHEREAS, Diamanti Construction and Development, Inc discovered additional
conditions that need to be addressed and that were not contemplated by the original
agreement; and
WHEREAS, Change Order 1 addresses four (4) inch Service Line Restoration for
$8250.00; and
WHEREAS, Change Order 2 addresses pump monitoring for the southern burst
for $18,173.82; and
WHEREAS, the City Commission finds that it is in the best interest of the City to
authorize the City Manager to execute Change Orders 1 and 2.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF OPA-LOCKA, FLORIDA:
Section 1. RECITALS ADOPTED.
The recitals to the preamble herein are incorporated by reference.
Section 2. AUTHORIZATION
The City Commission hereby authorizes the City Manager to execute Change Orders
1 and 2 to the agreement with Diamanti Construction and Development, Inc., for Bahman
Avenue Phase II sanitary sewer construction, in an amount not to exceed twenty-six
thousand four hundred twenty-three dollars and eighty-two cents ($26,423.82).
Resolution No. 19-9600
Section 3. SCRIVENER'S ERRORS.
Sections of this Resolution may be renumbered or re-lettered and corrections of
typographical errors which do not affect the intent may be authorized by the City
Manager, or the City Manager's designee, without need of public hearing, by filing a
corrected or re-codified copy of same with the City Clerk.
Section 4. EFFECTIVE DATE.
This Resolution shall take effect immediately upon adoption and is subject to the
approval of the Governor or his designee.
PASSED AND ADOPTED this 16'x' day of January, 2019.
zzote
Mayor Matthew Pigatt
Attes to: Approved as to form and legal sufficiency:
Joa . Flores THE BROWN LAW GROUP, LLC
City lerk City Attorney
Moved by: COMMISSIONER KELLEY
Seconded by: VICE MAYOR DAVIS
Commissioner Vote: 5-0
Commissioner Burke: YES
Commissioner Kelley: YES
Commissioner Bass: YES
Vice-Mayor Davis: YES
Mayor Pigatt: YES
ooa:�oc+e
�4 f4'Y�r1
I1�
City of Opa-Locka
Agenda Cover Memo
Department Airia Austin Department
Director: Director Signature:
Finance Director: Bryan Hamilton FD Signature:
Department
Acting City Newall Daughtrey CM Signature: •
Manager: J. •
Commission 01/23/2019 Item Type: Resolution O inane 141 er�
Meeting Date: X
(EnterX in box)
Fiscal Impact: Ordinance Reading: 1st Reading 2nd Reading
(Enter X in box) Yes No (Enter X in box)
X Public Hearing: Yes No Yes No
(Enter X in box) x x
Funding Source: (Enter Fund Advertising Requirement: Yes No
Account#: &Dept) (Enter X in box) X
Ex:
35-535340
Contract/P.O. Yes No RFP/RFQ/Bid#:
Required: X
(Enter X in box)
Strategic Plan Yes No Strategic Plan Priority Area: Strategic Plan Obj./Strategy:
Related X Enhance Organizational IN (list the specific objective/strategy this
(Enter X in box) Bus.&Economic Dev D item will address)
Public Safety
Quality of Education D
Qual.of Life&City Image D
Communication
Sponsor Name City Manager Department: City Manager
Short Title:
A resolution authorizing the City Manager to execute Change Orders 1 & 2 in connection with
Bahman Avenue Project Phase II with Diamanti Construction&Development,Inc
Staff Summary:
City Staff, engineers, and contractor uncovered conditions on the project that were not contemplated by the BID
for Bahman Avenue Phase II project:
Change Order 1:4" Service Line Restoration for$8,250.00
Change Order 2: Pump Monitoring—South Burst for$18,173.82
Total change order cost for Bahman Avenue Project Phase II will be $26,423.82.
Proposed Action:
Staff recommends approval.
Attachment:
1. Agenda
2. Change Order 1:4" Service Line Restoration Proposal
3. Change Order 2: Pump Monitoring—South Burst Proposal
oQp.iocxa
o 0
j e
lI
• f�Lilp
c�n o ory
MEMO
TO: Newall J. Daughtrey, Acting City Manager
FROM: Airia Austin,CIP&PWD Director
DATE: January 15,2019
RE: Bahman Avenue Projects-Change Orders for Phase I &Phase II
Change Order#1-North Burst:
During the sewer pipe installation north of Pump Station 11A, the by-pass pump failed several
times during the night hours. It caused sewage to overflow into the excavated work area. The
contractor had to clean it up each time, which resulted in job delay
Change Order#2-South Burst:
During the sewer pipe installation south of Pump Station 11A, the by-pass pump failed several
times during the night hours. It caused sewage to overflow into the excavated work area. The
contractor had to clean it up each time, which resulted in job delay. The City directed the
contractor to monitor the bypass pump after hours to assure no more sewage overflow.
Change Order#3-Pipe and Valve Repair:
4" water main in the inter section of Sharazad Blvd and Bahman Ave needed repair due to
construction activity and age of the pipe caused crack on the line. The contractor provided the
pipe and materials needed to fix it.
Change Order#4-Milling& Resurfacing:
The contractor recommended milling and resurfacing the entire Bahman Avenue section
between Sharazad Blvd and Dunad Ave. The initial work was estimated only for the disturbed
area (5000sf out of 24,100sf). Milling and resurfacing the whole street was agreed upon by the
City and contractor. The road was resurfaced and brick pavers and sidewalks were installed.
***END OF MEMORANDUM***
DI 4IANTI CONSTRUCTION & DEVELOPMENT, INC
STATE LICENSE#06:0 1524241
October 24, 2018
4" Service Line Restoration
Item Quantity Unit Unit Price Total Cost
Labor 1 LS $3,000.00 $3,000.00
Excavation/Pavement Restoration 1 LS $4,500.00 $4,500.00
CONSTRUCTION COST $7,500.00
Admin Fee (10%) 1 LS $750.00 $750.00
TOTAL $8,250.00
Sincerely,
M. Saif Islam
ro
EMAIL: Di. 'ICONSTRUCTION 4 IL.00 , CEJJ.:561-801-7191
q- r
"' x
„ • A Document G701' - 2017
Change Order..
5: T: am
ad w
CONTRACT "ON: CHA Met INFORMATION:
t 8ahman A.Me II 15" er Conine Far:Emergency a5 ? Repair i, Order Number.Phase II-01
.. t-'a Date:06/252018 Data 11/15/2018
r�,
: .�h ARCHITECT:(Name and address) OOIITRACTOIC(Name ardaatrb+tss)
iliAr Dismauti C,am ion&Dev.Inc
y�
SS . r } -
v a a r S
' iE :
iis 1 4forfR rAe arl if'appliaobds,attach or reference specific sxhibite.Alto include ag►ee�dspot adfrAluentf
li
4t 5e
r r a �, *
$ 302,800.00° ,T� f 0.00
ry lkk ' �joge Order was 8 302,800.00 r u '
_
A be by dus Oeidar Order in the will be amount of $ 18,173 82' 8410'this k5 :�. �.,' .q w 320,973 82
M ' by 60(0)days.
' . .$gb+ti�R111Lpietiou will be 11/30/2018
'' �' x'- Th ®ate''`does neE a adjustmaas to the Contract Sum or Guaranteed Maximum Price,or the Contract
�1z � �
zire Change Directive until the coat and time have been
agreed upon b}'both the
. which c e t►Change Order is executed to supersede the Construction Change
Directive.
;z, 1 ( ED o
stiliECT,CONTRACTOR AND t�glltTiR.
. x;[Cq, `0 Drtiaaati Coee IRR
*, .t. *a0;, Dfwalopmeat, CrtyOfOpa-IOdca
s:lb. ? Inc
iftimecr(b OR(Firm none) OtNER(Finn nowt)
-9,3,...4,7,,,,N.,
,
"" 1aiTRE .' a: ; . TURF
SIGNATURE 4
Mohammed S Islam+ 1 1 E PRINTED E AD TITLE PRINTED NA lii I!AND TITLE
z ,, at �. .
, " 11/15/2018
,.. DATE DATE DATE
1c
4
-Nr zr�2',V r
xya S . .
AIA tI061mw OTM"—nil.Capytipla019Th.1ae7.2000.2001 a 1 2017 by his Madam Ii la al AIcMs la.Al de&Nsuved.WAMIfi:TMs
AlA 'eftw set is pwlaeled by U.1.Cspyrl4F!Law and bdwaarotrl Tredlaa LMtavrfor4ad naproduelton or diatt�tdan d ties AM naafwafR ate
a poraon of It awy weal{a aarafeo clvi and f AaMI pfafddra.and wet ba pfaaafnAod b afa awaYafan aaMtr paaaade m id.,a>ta law.THIr
time Nolan Pwduesd by AlA roawaw al 232S20 tT an 1111 1b wldot Ordot No.75100."the su ch aquas on 1111 W2010,aid k not lam wadu
Diamanti Construction&Development,Inc
Project Name: Bahman Ave Phase II Sewer Line Repair
Change Order name: Bypass pump monitoring-South Burst-Phase II
Date Submitted: 11115/20.0
Change Order number: ?haw II-01
Days Requested
Equipment
Description QTY Unit Day Rate Total
225 Excavator 1.5 Day $1,073.00 $ 1,609.50
Loader 1.5 Day $799.00 $ 1,198.50
Skid Steer Day $260.00 $
Foreman Truck 1.5 Day $60.00 $ 90.00
Dump Truck 1.5 Day $360.00 $ 540.00
Construction Broom Day $147.00!WIN
6"Hoses,Header Pipe and Accessories 1.5 Day $67.00 $ 100.50
Sediment Tank Day $250.00 $
6"Suction Pump 1.5 Day $268.00 $ 402.00
Two 4x20 hoses(Suction) 1.5 Day $20.00 $ 30.00
One 4x50 lay flat(Discharge) Day $10.00 $
4"Strainer Day $5.00 $ -
Small Tools 1.5 Day $15.00 $ 22.50
Trench Box 1.5 Day $145.00 $ 217.50
$ 5,395.50
Labor Days Day Rate
Superintendent Day $464.00 $696.00
Foreman Day $363.00 $544.50
Operator IMO Day $714.00 $1,071.00
Project Manager 0.75 Day $519.00 1111111111111153
$4,433.25
Subcontractor
Pump Monitoring-1 week 1 Day $ 6,692.90 $6,692.90
56,692.90
Materials
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Total Construction Cost: $16,521.65
Admin Fees-10% $1,652.17
Total $18,173.82