RESOLUTION AUTHORIZING A PROFESSIONAL SERVICES CONTRACT FOR
ENGINEERING SERVICES WITH T &M ASSOCIATES -
TURNPIKE SEWER CROSSING CONSTRUCTION OBSERVATION
& CONTRACT ADMINISTRATION SERVICES
WHEREAS, the Borough of Carteret is in need of engineering services in regard to the New
Jersey Environmental Infrastructure Trust Project, Turnpike Sewer Crossing Construction
Observation & Contract Administration Services; and
'YHEREAS, the Borough's Consulting Engineers, T&M Associates, possess the requisite skill
and expertise for said services; and
'VHEREAS, T&M Associates has submitted a proposal to provide said engineering services at a
total cost not to, exceed $102,500.00; and
WHEREAS, the Mayor and Council have reviewed said proposal;
WHEREAS, the Chief Financial Officer has certified that funds are or will be available for said
purpose.
NO\Y, THEREFORE, BE IT RESOLVED by the Mayor and Council of the Borough of
Carteret, County of Middlesex, State of New Jersey, as follows:
1. That the proposal from T &M Associates for engineering services in regard to the
New Jersey Environmental Infrastructure Project, Turnpike Sewer Crossing
Construction Observation and Contract Administration Services at a total cost not
to exceed $102,500.00 at the rate set forth in T&M's existing contract with the
Borough is hereby approved.
2. That annexed hereto is a copy of said proposal.
3. That this action is approved as an 'award of a professional services contract
pursuant to N.J.S.A. 40A:ll~5(1)(a) in accordance with the Borough's Fair and
Open Process as authorized by law.
4. That a copy of this resolution be forwarded to the Borough's Purchasing
Department and T &M Associates.
Adopted this 22"' day of July, 2010
and certified as a true copy of the
original on July 23, 2010.
KATHLEEN M. BAfu'lEY, NhvlC
Municipal Clerk
~
RECORD OF COUNCIL VOTE
COUNClLi\L\N YES NO NV A.B. COUNCIUIAN YES NO NV A.B.
BELLINO X KRUfl X
i DIAZ X NAPLES . X
D(f~\SCIO X X
SITARZ
x - Indicate VOle AB-Absent NV - Not Voting XOR - Indicates VOle to Overrule Veto
II Adopted at a meeting of the l\'funicipal Council
~t!llY~
.1 ;>;, Z~;~ LE. .... ;~u
1373 BROAD STREET, SUITE 306, CLIFTON, NJ 07013-4231
(973) 614-0005 * lax (973) 614-0025 * www.tandmassociates"com
-aM
ASSOCIATES
CART-01820
July 12, 2010
Mayor Daniel J. Reiman
Borough of Carteret
Municipal Building
61 Cooke Avenue
Carteret, NJ 07008
Re: Turnpike Sewer Crossing
Construction Observation ani! Contract Administration Services
Dear Mayor Reiman:
The Borough has awarded a construction contract for the Turnpike Sewer Crossing project to Cruz
Contractors, LLC in the amount of$2,273,515.00. As you are aware, the project is funded through the NJ
Environmental Infrastructure Trust (EIT) Program.
As requested we are prepared to provide contract administration and field inspection services for the
project. Our Construction Services Manager and I will coordinate project construction inspection
activities. The following is a description of the services we will provide, the anticipated perfonnance
period for these services and the budget for the cost of same.
The following scope of services is proposed for the project.
A. Utility Aureements and Auencv Coordination - Bid Phase
1. PSE&G - Provide sewer easement documents to PSE&G; assist Borough Attorney and appraisai
consultant in review of agreement requirements and inclusion of pertinent provisions in bid
documents.
2. Conrail- Review of License to Cross with Conrail and Borough representatives and inclusion of
"insurance and other agreement requirement in bid documents.
3. NJ Turnpike Authority - Review of License to Cross with NJT A and Borough representatives
and inclusion of insurance and other agreement requirement in bid documents.
4. Final modifications to bid documents and discussions in accordance with NJDEP requirements
and discussions and various submissions to NJDEP to Dbtain required "authorization to bid."
B. Bid Phase Services
1. Advertise the project for bidding on behalf of the Borough.
ENGINEERS * PLANNERS * LANDSCAPE ARCHITECTS * ENVIRONMENTAL SCIENTISTS * SURVEYORS
CIVIL' ELECTRICAL' ENVIRONMENTAL' MECHANICAL' MUNICIPAL' SITE * SOLlO WASTE' STRUCTURAL * TRAFFiC * TRANSPORTATION
CORPORATE HEADQUARTERS IN MIDDLETOWN, N,} / REGIONAL OFFICES: TOMS RIVER, NJ; MOORESTOWN, NJ; PLYMOUTH MEETING, PA; and SAN JUAN, PUERTO RICO
Le: Mayor Daniel J. Reiman
'1!M
ASSOCIATES
CART 01820
July 12,2010
Page 2
Re: Turnpike Sewer Crossing
Construction Observation and Contract Administration Services
2. Respond to questions from potential bidders during the bid period.
3. Attend the receipt of bids with appropriate municipal officials.
4. Assist the Borough with the bid review process including an evaluation of the contractor's bid
submissions. Prepare a bid tabulation comparing the bids received, review the credentials of the
low bidder, and prepare a recommendation of award for Borough action.
C. Construction Phase Services
I. Contract Administration
Submit required docwnents to DEP to secure Authorization to Award.
Once a contract has been awarded, we will prepare contracts for review by the Borough
Attomey and execution by the Contractor and the Borough.
Arrange for and attend a preconstruction meeting with the contractor, Borough
representatives, Police Department, PSE&G, NJ Turnpike Authority (NJTA), Conrail, the
NJDEP, and affected utility owners including but not limited to:
. MCllWORLDCOMM
. Verizon
. VVilliarns-Transco
. Chevron
. Buckeye
. Colonial
. Sprint
. AT&T
. Adesta
Prepare for and attend progress meetings with representatives of the Borough, Contractor,
DPE, and agencies/utilities. Tlus scope of services asswnes I progress meeting per month
during construction plus an additional meeting during the microtunneling work.
Provide contract administration services during constmction of the project. including
correspondence, review of payment requests, preparation of payment celiificates, and review
of extra requests, and review and preparation of change orders, as required. The contract
period is 240 days.
2. Shop and Setting Drawings and Sublnittals Review
Review schedule, shop drawings for sewer pipe, manholes, slide gates, microtunneling work,
pipe lining, and other specific items of work. For the purpose of this scope of services, it is
assumed the initial SUblnittal is for items generally as specified in the contract docwnents; the
Contractor's submittals are complete; and an initial review for completeness has been
Le: Mayor Daniel J. Reiman
-aM
ASSOCIATES
CART 01820
July 12,2010
Page 3
Rc: Turnpike Sewer Crossing
Construction Observation and Contract Administration Services
performed by the Contractor. The review estimate includes one resubmittal to respond to
comments in the initial submittal. In order to maintain the proposed budget, partial or
incomplete submittals will be returned without review.
Review of major substitutions or revised designs is considered beyond this scope of services.
Should these services be required it is assumed the contractor would be responsible to cover
the related engineering costs.
3. Utility/Agency Coordination
Coordination and meetings with PSE&G, NJ Turnpike Authority, and Conrail before and
during the construction of the project. The task includes efforts related to monitoring
compliance with the agreements and licenses and regnlations of the above agencies. A
maximum of2 meetings with each agency is included in this scope of services.
Coordination and meetings with the utilities that will be crossed by the sewer construction
and microtunneling. This task includes efforts related to monitoring compliance with
requirements of utilities with respect to crossings and includes a maximum of 2 utility
coordination meetings.
Any new requirements from agencies/utility companies not noted herein are considered extra
work outside of the scope of services and fee estimate.
4. Field Inspection Services
Provide construction observation services to monitor the progress and quality of the executed
work of the contractor and to determine, in general, if such work is proceeding in accordance
with the Contract Documents. The Engineer shall not be responsible for the means, methods,
techniques, sequences, or procedures of construction selected by contractors or the safety
precautions and programs in incident to the work of contractors. Field inspection efforts will
be directed toward providing confidence for the Owner that completed work of contractor
conforms to the contract docwnents, but the Engineer shall not be responsible for the failure
of the contractors to perform the work in accordance with the Contract Documents. On the
basis of on-site observations, the Enginecr will kccp the Owner informed on the progress of
the work, and shall endeavor to guard the Owner against defects and deficiencies in such
work, and may disapprove or reject work failing to conform to the Conlract Documents.
Full time construction observation services are proposed during open cut pipe and manhole
installation, and part time construction observation services are proposed as follows during
microtunneling pit constlUction, microtunneling of 48" casing pipe, insertion of carrier pipe,
and the lining work and other related work to complete project.
. Microtunneling pits - 6 weeks at 20 hrs/week
. Microtunneling - 19 days @ 8 hrsIday
. Carrier pipe installation- 3 days @ 8 hrs/day
. Testing/Restoration - 4 weeks @ 20 hrsIweek
. Lining - 5 days @ 4 hrsIday
Le: Mayor Daniel J. Reiman
-aM
ASSOCIATES
CART 01820
July 12,2010
Page 4
Re: Turnpike Sewer Crossing
Construction Observat.lon and Contract Administration Services
It is anticipated the microtunneling of the casing once started will continue 24/7 (24 hours per
day / 7 days per week) and will take approximately 18-20 days. This scope of services
assumes an overall 5 month period of active construction.
5. Project Closeout and One Year Certification
Once construction has been completed, review videotape of completed sewer installation,
existing interceptor, and new lining work; prepare final punch list and closeout the project.
Conduct a final inspection of the project with the Owner.
Prepare fmal payment celtificate and change order and transmit closeout documents to the
Borough.
Prepare record drawings of the completed construction. The contractor is required by contract
to provide record information to assist the Engineer in the preparation of record drawings.
The as-built drawings for the NJT A will be prepared using microstation software as required.
Conduct an inspection of the project with the NJDEP and the Owner one year after project
completion and prepare the One Year Certification as required by the NJDEP.
Fee Pronosal
We propose to provide the services outlined in the Scope of Services for a fee not to exceed $120,500
invoiced monthly in accordance with our 2010 Municipal Engineering contract in accordance with the
following task breakdown:
A. Utility/Agreements and Agency Coordination - Bid Phase
B. Bid Phase Services
C. Construction Phase Services
1. Contract Administration including NJDEP and NJEIT
Program Requirements
2. Shop & Selling Drawings and Submittals Review
4. Utility/Agency Coordination
3. Field Inspection Services
5. Project Closeout and One Year Certification
Total
$9,500
$8,500
$11 ,500
$7,500
$13,500
$65,000
$5,000
$12U,5UU
Should additional services outside of this scope of services be required, we will immediately notify the
Borough and will provide a cost for the additional work. No additional work will be perfOlmed without
prior approval of the Borough.
Le: Mayor Daniel J. Reiman
11M
ASSOCIATES
CART 01820
July 12, 2010
Page 5
Re: Turnpike Sewer Crossing
Construction Observation and Contract Administration Services
If you have any questions or require any additional information, please call.
Very truly yours,
T&M ASSOCIATES
jJ,W~
DONALD J. NORBUT, P.E., C.M.E.
CARTEREr BOROUGH ENGlNEER
DJN:JJM:scb:k:im