HomeMy Public PortalAbout19-9640 Agreement with Hernandez Underground for repairs of 1226 Jann Avenue Sponsored by: City Manager
RESOLUTION NO. 19-9640
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF OPA-LOCKA, FLORIDA, AUTHORIZING THE CITY
MANAGER TO TAKE IMMEDIATE ACTION AND ENTER
INTO AN AGREEMENT WITH HERNANDEZ
UNDERGROUND TO REPAIR A 12" SEWER GRAVITY MAIN
IN THE AREA OF 1226 SHARAR AVENUE, IN AN AMOUNT
NOT TO EXCEED $27,500.00; IN A FORM THAT IS
ACCEPTABLE TO THE CITY ATTORNEY; PROVIDING
FOR INCORPORATION OF RECITALS; PROVIDING FOR
AN EFFECTIVE DATE.
WHEREAS, A 12" gravity main in the area of 1226 Sharar Avenue is in need of
immediate repair; and
WHEREAS, The City Commission believes that it is in the City's best interest to
authorize the City Manager to take immediate action to effectuate the said; and
NOW THEREFORE, BE IT RESOLVED THAT THE CITY COMMISSION
OF THE CITY OF OPA-LOCKA, FLORIDA:
Section 1. The recitals to the preamble herein are incorporated by reference;
Section 2. The City Manager is hereby authorized to take immediate action to repair
the 12" gravity main in the area of 1226 Sharar Avenue, by entering into an
agreement with Hernandez Underground, for said services, in an amount not to
exceed $27,500.00, and in a form that is acceptable to the City Attorney.
Section 3.
Sections of this Resolution may be renumbered or re-lettered and corrections of
typographical errors which do not affect the intent may be authorized by the City
Manager, or the City Manager's designee, without need of public hearing, by filing a
corrected copy of same with the City Clerk.
Section 4. This Resolution shall take effect immediately upon adoption, and is subject
to the approval of the Governor of the State of Florida or his designee.
PASSED AND ADOPTED this 10th day of April, 2019.
Resolution No. 19-9640
Matthew A. Pigatt
Mayor
Attest to: Approved as to form and legal sufficiency:
rn
JoarL Flores Vincent T. Brown, Esq.
City Clerk The Brown Law Group, LLC
City Attorney
Moved by: COMMISSIONER BASS
Seconded by: VICE MAYOR DAVIS
Commissioner Vote: 4-0
Commissioner Kelley: NOT PRESENT
Commissioner Bass: YES
Commissioner Burke: YES
Vice Mayor Davis: YES
Mayor Pigatt: YES
City of Opa-Locka
Agenda Cover Memo
Department Airia Austin Department
Director: Director Signature:
Finance Director: FD Signature:
Department
Acting City Newall Daughtrey CM Signature: / wf
Manager:
Commission 04/10/2019 Item Type: Resolution I rdina c• S the
Meeting Date: X
(EnterXin box)
Fiscal Impact: Ordinance Reading: 1St Reading 2nd Reading
(EnterXin box) Yes No (EnterXin box)
X Public Hearing: Yes No Yes No
(EnterXin box) X X
Funding Source: (Enter Fund Advertising Requirement: Yes No
Account# &Dept) (EnterXin box) X
Ex:
35-535523
Contract/P.O. Yes No RFP/RFQ/Bid#: RFP#
Required: X Waive of BID
(EnterXin box)
Strategic Plan Yes No Strategic Plan Priority Area: Strategic Plan Obj./Strategy:
Related X Enhance Organizational •• (list the specific objective/strategy this
(Enter X in box) Bus.&Economic Dev item will address)
Public Safety
Quality of Education 0
Qual.of Life&City Image
Communication 0
Sponsor Name City Manager Department: City Manager
Short Title:
Request for waiver of bid for the emergency procurement, approving the hiring of Hernandez
Underground at a sum of$27,500.00,and authorizing the City Manager to enter into an agreement.
Staff Summary:
The purpose of this request is to take emergency action to repair a 12"sewer gravity main,due to the potential
for sanitary sewer overflow,and to protect residential health and safety immediate action is necessary
Proposed Action:
Staff recommends approval of this proposal.
Attachment:
1. Agenda
2. Hernandez Underground Proposal
3. Memo of explanation
"THE GREAT CITY"
pp oCka /
gloratt
o
1 i
MEMORANDUM
TO: Newall Daughtrey, Acting City Manager
FROM: Airia Austin, Public Works Director (I-017—, •
DATE: April 5, 2019
RE: Formation of Sinkhole
In the latter part of the month of March, we witnessed the preliminary signs of gravity main
failure adjacent to the residence located at 1226 Sharar Avenue. In this vicinity there are two
gravity mains one 12" and the other 16". This request is being brought before the commission as
an add-on item, at the April 10 Meeting.
We are confident the problem is with the smaller main, since we are experiencing slower than
normal flows between manholes
The intent is to perform a point repair, in lieu of replacing the entire section of pipe between
manholes, since this will be a costly venture. We have received three proposals for this repair
and the intent is to go with the low bidder Hernandez Underground.
Vendor Short Description Cost
Hernandez Underground Excavate area to set well point system, $27,500.00 Does not
install trench box, expose and repair include permit fees
damaged 12"main. Restore area
FD Majestic Services, Inc. Install well point system, install trench $38,500.00 Does not
box and shoring as needed, excavate to include permit fees
expose 12" gravity clay pipe, replace
20' section, and restore area.
Metro Equipment Services, Install well point system, install trench $40,500.00 Does not
Inc. box and shoring as needed, excavate to include permit fees
expose 12" gravity clay pipe,replace
20' section, and restore area.
780 FISHERMAN STREET,OPA-LOCKA,FLORIDA 33054(305)953-3058
AN EQUAL OPPORTUNITY EMPLOYER AND DOES NOT DISCRIMINATE ON THE BASIS OF HANDICAP
PROPOSAL
It.ri It LL�L
U N D E R G R O U N D
1520 SW 119 TERRACE DATE: April 3, 2019
Davie, FL 33325
Phone 786-514-1107 Fax 954-885-5554 FOR: 1226 SHARAR AVE
hernandezundergroundecomcast.net
AU: OWEN CARNEY
To: CITY OF OPALOCKA
OCARNEY @OPALOCKAFL.GOV
786-877-4015
DESCRIPTION AMOUNT
MAINTENANCE OF TRAFFIC
EXCAVATE AREA TO SET WELL POINT SISTEM WITH SAND BOX
SET TRENCH BOX
EXCAVATE AND EXPOSE BROKEN 12"CLAY
REPAIR BROKEN MAIN WITH 2 IMAX COUPLING AND C-900 PVC PIPE
CLEAN SEWER SISTEM MANHOLE TO MANHOLE
BACK FILL AND COMPACTED
RESTORE AREA
$27,500.00
PERMIT FEES, BONDS AND POLICE OFFICER ARE NOT INCLUDED!
THANK YOU FOR YOUR BUSINESS!
PROPOSAL
FD MAJESTIC SERVICES, INC.
OD BS d/b/a D B S G, L L C
GROUP 9950 S.W. 168 Terrace. Miami, FL 33157
TEL: (954) 642-6396 •
E-MAIL:jfernandezbrun @yahoo.com
Proposal Submitted To: Phone: Date:
City of Opa-Locka (305)953-2828 March 27,2019
Street: Replace 20 feet section of 12"gravity line
12950 N.W. 42nd Avenue
City,State and Zip Code: Job Location:
Op-Locka, Florida 33054 1226 Sharad Avenue, Opa-Locka, Florida 33054
Attention: Date of Plans: E-mail address: Fax Phone:
Mr Owen H. Carney E-mail : N/A
We are pleased to submit for your consideration this proposal to provide "Labor, material, equipment, M.O.T, and
supervision to complete the following work:
1. Set up M.OT.
2. Install complete well point dewatering system
3. Install Sheeting(trench box)and shoring as needed
4. Excavate to expose broken 12"gravity clay pipe
5. Plug in 12" line inside up-stream manhole
6. Cut 12"Clay pipe and remove a section not to exceed 20' in length
7. Prepare#57 rock bed to lay new C-900 PVC sewer pipe
8. Replace about 20' of 12" C-900 pipe using two 12" macro HP extended range coupling 2-12 manufactured by
Romac Industries or equal
9. Place 6" layer of#57 rock on top of the pipe
10. Back fill and compact in 12' layers at 98%density
11. Set up vactor truck on west manhole to jet and vacuum line from the point of repair to this manhole
12. Close circuit T.V. line and provide copy of video
13. Remove plug from up-stream manhole.
14. Restore about 1800 square feet bahia sod
15. Restore±250 square feet of asphalt to meet existing condition
16. Remove and dispose debris and trash
17. And all other material,and tools to provide a complete working rapair
18. Final clean up
INCLUSIONS
Limited MOT
Up to 250 Square feet of paving restoration
The discharge of the groundwater will de done into the existing storm drainage
system
EXCLUSIONS
➢ Sod not included ➢ Permits
➢ Assestment or remediaton and all special handling,removal or ➢ Plans if required to be provided by the
disposal of contaminared soil or ground water owner
➢ Any additional mobilization besides the first one.The job must be ➢ Any deviation from the outline of this
allowed to continue without interruptions until completed proposal
➢ Any paving above and beyond de 250 S.F.per repair will be done as ➢ Police Protection
an extra at a cost of$5.5 per square feet ➢ Payment and performance Bond
➢ Relocation of utilities ➢ Conflict encountered during construction
➢ Sewer By-pass
PAYMENT TERMS: Based upon Applications for Payments to be discussed upon approval of contract.
with the signing of this proposal
Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at the following rate:any
balance past thirty(30)days will be subject to 1-2%per month(18%per annual)finance charge with the Owner/Agent paying for all
attorneys'fees should collection be necessary.
This proposal may be withdrawn by FD MAJESTIC SERVICES, INC.d/b/a DBSG if not accepted within 30 days
DISCLOSURES
713.015 LIEN LAW DISCLOSURE
According to Florida's Construction Lien Law(Sections 713.001—713.37,Florida Statutes),those who work on your property or provide materials and who are not paid
in full have a right to enforce their claim for payment against your property.This claim is known as a Construction Lien.If your Contractor or a Subcontractor fails to pay
Subcontractors,sub-subcontractors,or material suppliers or neglects to make other legally required payments,the people who are owed money may look to your
property for payment,even if you have paid your contractor in full.If you fail to pay your contractor,your contractor may also have a lien on your property.This means
if a lien is filed your property could be sold against your will to pay for labor,materials or other services that your contractor or a subcontractor may have failed to pay.
Florida's construction Lien Law is complex an it is recommended that whenever a specific problem arises,you consult an attorney
We propose hereby to furnish material and labor complete in accordance with above specifications,for the sum of:
Thirty Eight Thousand Five Hundred Dollars and no cents $ 38,500.00
I.'ayment to be made as follows: wiTn the oraer ana me rest upon completion OT me now test
All material is guaranteed to be as specified. All work to be completed in a workmanlike Authorized Signature:
manner according to standard practices. Any alteration or deviation from above
specification involving extra costs will be executed only upon written orders, and will
become an extra charge over and above the estimate. All agreements contingent upon
strikes,accidents or delays beyond our control. Owner to carry fire,tornado and other Dagoberto Castillo
necessary insurance. Our workers are fully covered by Workmen's Compensation
Insurance. Note:This proposal may be withdrawn by us if not accepted within 30 days.
Acceptance of Proposal
The above prices, specifications and conditions are satisfactory and are hereby
accepted. You are authorized to do the work as specified. Payment will be made as
outlined above.
Signature
Date of acceptance:
TO: City of Opa-Locka Project: Emergency Repair of 10"Gravity Sewer main
12950 NW 42 AVE 1226 Sharar Avenue
Opa-Locka,Florida 33054 Opa-Locka,FL
Att.: Owen H.Carney Engineer:None
SCOPE OF WORK.-
Subject to a mutually acceptable agreement,Metro Equipment Service,Inc.("MES") proposes to provide,in accordance with the following qualifications and
exceptions,all labor material and equipment to perform and complete the sewer repair items referenced under"Scope of Work- Price Schedule".
1 Set up M.OT.
2 Install complete well point dewatering system
3 Install trench shoring(trench box)as needed
4 Excavate to expose broken 12"gravity clay pipe
5 Plug in 12"line inside up-stream manhole
6 Cut 12"Clay pipe and remove a section not to exceed 20'in length
7 Prepare#57 rock bed to lay new C-900 PVC sewer pipe
8 Replace about 20'of 12"C-900 pipe using two 12"macro HP extended range coupling 2-12 manufactured by Romac Industries or equal
9 Place 6°layer of#57 rock on top of the pipe
10 Back fill and compact in 12'layers at 98%density
11 Set up Vactor truck on west manhole to jet and vacuum line from the point of repair to this manhole
12 Close circuit T.V.line and provide copy of video
13 Remove plug from up-stream manhole.
14 Restore about 1800 square feet Bahia sod
15 Restore±250 square feet of asphalt to meet existing condition
16 Remove and dispose debris and trash
17 And all other material,and tools to provide a complete working repair
18 Final clean up
QUALIFICATIONS AND EXCEPTIONS:
1 Price is based on Contractor being able to discharge the groundwater dewatering into the existing drainage system or sewer system.
2 Contamination assessment or remediation work for contaminated soil,sediments and/or groundwater is not included.Removal and replacement of unsuitable and/or
3 MOT is included.Off-duty police is not included.MOT plans signed and sealed by PE is not included.
4 Cleaning and TV inspection of the sewer line associated with the repair is included.Video will be performed from MH to MH
5 This proposal is predicated on the assumption that MES will perform all the work included in this scope of services.
6 City,county,state or federal special prevailing wages are not included in our price.
7 Costs of payment and performance bond premiums are excluded. Bonds can be provided upon request.Cost of the bonds shall be reimbursed to Metro.
8 All permit fees are excluded.All permits procurement to be by others.All impact and utility connection fees are excluded.
9 All construction staking and layout is excluded. MES to provide redline as-builts at the completion of MES's scope.
10 All work to be performed in one mobilization.Additional mob/demob are not included.
11 Relocations of existing utilities are excluded.Conflicts encountered during construction will be negotiated prior to the work being performed.
12 Sewer By-Pass is Excluded
13 Sheeting is excluded
14 Items included in this Exception list are meant to represent examples of general items excluded from the proposal,absence of an item from this list should not be
15 Progress payments to MES will be made by the City within 30 days of the completion of the work as per submitted Monthly Payment Request.
16 Final payment to MES will be made by the City within 30 days of completion of MES scope of work.
17 Price is valid for 30 calendar days from the date of this proposal.
18 The work will be performed to meet OSHA regulation and the State of Florida Trench Saftey Act.
SCOPE OF WORK- PRICE SCHEDULE(LUMP SUM PROPOSALI
Description Ill WErelagaMI AMOUNT
1 Emergency Sewer Line Repair I LS 1 $ 40,500.00
TOTAL THIS PROPOSAL : $ 40,500.00
Ovp-LOCk4
0S 0
9
ii I O.
`
D
t\ 1� V? Y
APRIL 2019
Project Description: Sinkhole Created by Collapsed Sewer Pipe
• A sink hole was created when the
existing 12" sewer pipe collapsed -:. a I ttiv -
between Ahmad St. and Kalandar St. I 0,4`
• 20ft. of C-900 pipe will replace the
clay pipe at the section that
collapsed. `""
'" .•.••
-�..•. sn~••N z_52..E
IN)
,.: . . :. Stlarar Ave. -,,.>
�s cr x 12^a.r rw x
x t4 �
�•: snf Q M .�
,,.MH 11A-16
ti
MH 11A-17 I >,•1 - ;17- ' z-
...':- 226 Sharar Av-
PLAN VIEW
rRestore Pavements Grass Area
Ira 16.1
Install+/-20ft. 12"C-900 Install Sewer
r Lateral
I
1 ' 1
I
I
MH-11A-17 I MH-11A-16
RIM Elev.=8.88' RIM Elev.=8.47'
E inv.elev.=0.64'(12"Clay) E inv.elev.=0.59'(12"Clay)
W inv.elev.=0.53'(12"Clay)
LONGITUDINAL VIEW