MATHEI
ONSULTING INC. F��ecT??
Environmental Engineers _ _y
December 16, 1999
Kristin K. Garrison, AICP
Town Manager
TOWN OF GULF STREAM
100 Sea Road
Gulf Stream, Florida 33483
Dear Ms. Garrison:
Town of Gulf Stream
Stormwater Pump Station — Task 11-A
Mathews Consulting, Inc. (MC) is pleased to submit herewith the scope of services, project schedule, and
fee budget for Engineering Services for the referenced project.
Scope of Services
Subtask I — Survey
MC shall furnish the services of a professional surveyor to perform a topographic survey of the project
area. The topographical survey data will be prepared in AutoCAD (Version 14).
Subtask 2 — Design
MC shall design new stormwater pump station, detention area(s), piping, and new outfall for the design
project area as shown in Attachment 1. Design elements shall include:
• Delineating basin area that will convey stormwater to the new pump station.
• Stormwater pump station consisting of two (2) 20 CFS axial flow pumps, back-up generator,
including all appurtenances for a complete working system.
■ Pipes (e.g. size, length, type) and catch basins.
• Determine location and pipe size of new outfall.
■ Detention area consisting of enlarging Elsies Pond located at the Little Club Golf Course from 0.25
acres to a minimum size of 0.5 acres. In order to meet SFWMD water quality requirements, design
will also consider using Pond `B" at Little Club Golf Course. It is assumed that provision of water
quality beyond the detention ponds (e.g. road swales, etc.) is not required.
MC shall prepare technical specifications and construction drawings, which shall include: cover sheet,
general notes, plan/profile sheets, and detail sheets.
MC shall meet with Little Club Golf Course to coordinate project as needed.
Mathews Consulting, Inc. • 1601 Belvedere Road, Suite 215S • West Palm Beach, FL 33406.561-478-7961 • Fax 561-478-7964
Q
Drawings and specifications (two copies) shall be submitted to Town for review at the 90% and 100%
stages. MC shall meet with Town to review design documents, and incorporate comments into final
documents.
Prior to bidding, MC shall prepare a detailed opinion of probable construction cost based upon the
completed final design drawings and specifications, approved by the Town.
Subtask 3 — Permitting
MC shall prepare permit application and drawings to the South Florida Water Management District
(SFWMD). Associated permit application fees shall be determined by MC and paid by Town.
MC shall assist Town in consultations with the SFWMD. Consultation services shall include the
following:
• Attend up to two (2) meetings with SFWMD during review of the permit application.
• Respond to request(s) for additional information from SFWMD.
Note: Permitting services include modeling pre project analysis vs. post analysis to determine
allowable discharge rate. Comprehensive stormwater basin modeling is not included in this scope of
services.
Subtask 3 — Soil Testing
MC shall famish the services of a geotechnical engineer to perform soil borings at designated locations
within the project area.
Subtask 4 — Bidding
MC shall assist Town in advertising for and obtaining bids for construction. It is anticipated that work
shall be awarded under a single construction contract. MC shall provide 10 sets of bidding documents.
MC shall receive and process deposits for bidding documents and shall maintain a record of prospective
bidders.
MC shall attend pre-bid conference. MC shall issue addenda and provide supplemental information or
clarification, as appropriate, to all prospective bidders during the bid period.
MC shall review bids and provide recommendation for award of the construction contract.
Subtask S — Construction Administration
MC shall review and process shop drawings, samples, construction schedules, and certifications.
MC shall provide periodic inspection services for an expected construction period of 120 calendar days.
MC shall attend construction progress (4) meetings and provide a written summary of the issues
discussed.
MC shall review and certify contractor payment requests.
Q
mc.
MC shall certify to the South Florida Water Management District, based on the visible project features
and inspections that the project was constructed in accordance with the plans and specifications submitted
in the permit application.
Project Schedule
The completion dates for this work will be as follows (start date December 13, 1999).
Eneineering Services Time per Subtask Cumulative Time
Subtask 1-Survey(t)
6 weeks
6 weeks
Subtask 2 -Design
12 weeks
18 weeks
Subtask 3-Permittine
12-15 weeks
21 weeks
Subtask 5 -Bidding
6 weeks
27 weeks
Subtask 6 -Construction Admin.
16 weeks
43 weeks
t�) Subtask 4 -Soil Testing will be performed during Subtask I time period.
R) Subtask 3 -Permitting will overlap with Subtask 2 time period.
The compensation for services provided shall be billed on an hourly basis plus reimbursable expenses for
each subtask of work, up to the following not -to -exceed cost.
Subtask I -Survey
Subtask 2 -Design
Subtask 3 -Permitting
Subtask 4 -Soil Testing
Subtask 5 -Bidding
Subtask 6 -Construction Admin.
TOTAL PROJECT COST
$ 4,000.00
$ 17,000.00
$ 4,000.00
$ 3,000.00
$ 2,500.00
$ 6.500.00
$37,000.00 (Not -to -Exceed)
Work described herein is based on the assumptions listed below. If conditions differ from those assumed
in a manner that will affect the Scope of Work and schedule, MC shall advise Town in writing of the
magnitude of the required adjustments. Change in completion schedule or compensation to MC shall be
negotiated with the Town.
1. Town shall furnish MC available record drawings of existing facilities in the project area.
2. Town personnel shall assist in field verification of affected Town facilities.
3. Town will be responsible for acquisition of easements required for the project.
4. Contractor shall provide Town with final Record Drawings.
5. Design of Water Quality per SFWMD will consist of enlarging "Elsie Pond". Any design of
additional water quality treatment facilities required by SFWMD will be considered additional'
services and will be billed at our hourly rate.
AA�
CONSULTING 'NC
We are looking forward to working with the Town on this very important and challenging project.
Sincerely,
M T E� CONSULTING, INC.
David L. Mathews, P E.
Vice President
c: File No. 1062
ATTACHMENT 1
415' OUTFALL LINE -
TO INTRACOASTAL
I
i
PROPOSED 15'
DRAINAGE
EASEMENT
WRIGHT W
ll
i
i Ii
I i
I
x
_ I9,
o�
I �
Ih
� II
190' - 42' ADS
r
INTRACOASTAL WATERWAY _
1" = 120'
EW BULKHEAD
EXISTING #ALL I
TO BE AB ONED
I �
IA CH BASINS I. � - \ I
2' OUTFALL
2-20 CFS AXIAL PIP
FLOW PUMPS
i
i
AREA TO B
DREDGED
!f
x--150' OF b'
1 i ter, inn orcein
co Pt+ew
3
I Z LITTLE CLUB
GOLF COURSE
I
■ EXISTING CATCH BASIN
■ NEW CATCH BASIN
--- PROPERTY, R/O/W OR EASEMENT LINE
NEW DRAINAGE LINE
TOWN OF G JLFSTREAM
SKETCH OF 40 CFS AXIAL FiOW
KU28 TO NTRACOASTAL